1966-1988
CLIENT : SAIPEM
VESSEL : VARIOUS
LOCATION/PROJECT : Adriatic Sea - Egypt - Spain - Persian Gulf - West Indies - North Sea - East Africa
TYPE OF WORK
: Air and Saturation Diving - SAIPEM Diving Department

1989
CLIENT : SAIPEM / SCOP
VESSEL : Barge CASTORO 4
LOCATION/PROJECT : BASSORA (IRAQ)
TYPE OF WORK : Air diving services. Construction of shipping terminal
WORK DURATION
: 6 MONTHS

1989
CLIENT : SAIPEM / AGIP
VESSEL : DLB CASTORO 2
LOCATION/PROJECT : Off-Shore ANCONA (ITALY)
TYPE OF WORK : Air diving service. Pipe-laying assistance at BARBARA, ELENA, PENNINA, PCC Fields
WORK DURATION : 2 MONTHS

1989
CLIENT : SAIPEM / AGIP
VESSEL : DLB CASTORO 2
LOCATION/PROJECT : Adriatic Sea - Off-Shore RAVENNA - ITALY
TYPE OF WORK : Air diving service. Pipe laying, Post trenching assistance
WORK DURATION : 2 MONTHS

1990
CLIENT : SAIPEM /AGIP
VESSEL : DLB CASTORO 2
LOCATION/PROJECT : Adriatic Sea - Off-Shore PESCARA, ITALY - GIOVANNA PROJECT
TYPE OF WORK :Air diving service. Assistance Jacket installation
WORK DURATION : 2 MONTH
S

1990
CLIENT : SAIPEM / O.N.G.C.
VESSEL : DSV OCEAN DRIVE
LOCATION/PROJECT : BOMBAY HEIGHT FIELD (INDIA) - Gas Lift Project
TYPE OF WORK :Supervision and Pre-construction Survey for: Risers and spools pieces installation
WORK DURATION : 1 MONTH


1990
CLIENT : SAIPEM /AGIP
VESSEL : DLB CASTORO 2
LOCATION/PROJECT : ADRIATIC SEA
TYPE OF WORK :Air/Saturation diving service. Assistance Jacket & deck installation at GIOVANNA Ptf. Installation IDECO 2100 off-shore Crotone
WORK DURATION : 2 MONTH
S


1990
CLIENT : SAIPEM /AGIP
VESSEL : DLB CASTORO 2
LOCATION/PROJECT : Ionian Sea - Crotone - Italy
TYPE OF WORK :Air & saturation diving service. Assistance Jacket Installation LUNA Field
WORK DURATION : 2 MONTH
S

1990
CLIENT : SAIPEM / AGIP RECHERCHE CONGO
VESSEL : DLB CASTORO 8
LOCATION/PROJECT : CONGO - Zatchi Field Project
TYPE OF WORK :Air diving service. Assistance pipe-laying. Tie-in installation
WORK DURATION : 2 MONTH
S


1990
CLIENT : SAIPEM / AGIP
VESSEL : DSV RAVELLO
LOCATION/PROJECT : ADRIATIC SEA - AMELIA FIELDS Project
TYPE OF WORK :Air diving service. Assistance of Jackets installation AMELIA B - AMELIA C
WORK DURATION : 4 MONTH
S


1990
CLIENT : SAIPEM / AGIP
VESSEL : DSV RAGNO 2
LOCATION/PROJECT : ADRIATIC SEA - ANNABELLA Fields Project
TYPE OF WORK :Air and Saturation Diving service. Assistance installation ANNABELLA Ptf
WORK DURATION : 40 DAYS

1991
CLIENT : SAIPEM / MOBIL
VESSEL : DLB CASTORO 8
LOCATION/PROJECT :NIGERIA - EDOP-QUA Idoe Terminal Development Projectt
TYPE OF WORK :Air diving service. Assistance pipe-laying. 24" Tie-in installation
WORK DURATION : 2 MONTHS

1991
CLIENT : SAIPEM / AGIP
VESSEL : Barge AD2/D.S.V. ALBATROS
LOCATION/PROJECT : Off-Shore Adriatic Sea - Agostino Field Project
TYPE OF WORK :Independent Sub Contractor - LUMP SUM WORK. Risers installation, Construction & installation of 6 flanged Spools Pieces. Mattresses positioning. Flooding, Pigging, Hydrostatic final Test
WORK DURATION : 2 MONTHS

1991
CLIENT : SAIPEM / MOBIL
VESSEL : Various vessel
LOCATION/PROJECT :NIGERIA - EDOP-QUA Idoe Terminal Development Project
TYPE OF WORK :Air diving service. Survey operations
WORK DURATION : 50 DAYS

1991
CLIENT : SAIPEM / LIBYAN OIL STATE COMPANY
VESSEL : D.S.V. PALINURO
LOCATION/PROJECT : BENGASI, LIBYA
TYPE OF WORK :Independent Sub Contractor - LUMP SUM WORK. Air diving N.D.T. & General inspection RAS EL MUNGAR Jetty
WORK DURATION : 45 DAYS

1991
CLIENT : SAIPEM /MINISTRY of ENVIRONMENT
VESSEL : D.S.V. RAGNO 2
LOCATION/PROJECT : GENOA, ITALY - HAVEN Project
TYPE OF WORK : Air/Saturation diving. Inspection/Various works on the wreck of tanker HAVEN
WORK DURATION : 3 MONTHS

1991
CLIENT : AGIP PETROLI
VESSEL : Barge PORTUNATO
LOCATION/PROJECT : LA SPEZIA, ITALY - Wharf Project
TYPE OF WORK : Contractor - LUMP SUM WORK design, construction, Installation of refuelling wharf
WORK DURATION : 30 DAYS

1991
CLIENT : BESTETTI
VESSEL : Barge PORTUNATO
LOCATION/PROJECT : S.MARGHERITA LIGURE, ITALY - Wharf Project
TYPE OF WORK : Contractor - LUMP SUM WORK design, construction, Installation of recreation wharf
WORK DURATION : 30 DAYS

1991
CLIENT : SAIPEM / ARAMCO
VESSEL : DLB CRAWLER
LOCATION/PROJECT : YANBU / SAUDI ARABIA
TYPE OF WORK : Air diving service. Construction of Marine oil terminal facilities
WORK DURATION : 8 MONTHS

1991
CLIENT : SAIPEM / WEBCO
VESSEL : DLB CASTORO 8
LOCATION/PROJECT : ABUKIR - EGYPT
TYPE OF WORK : Air diving service. Cutting and re.installation of jacket. Assistance of 12" pipe laying
WORK DURATION : 2 MONTHS

1991
CLIENT : SAIPEM / AGIP
VESSEL : DLB CASTORO 8
LOCATION/PROJECT : ANGOLA - SAFUERIO Field project
TYPE OF WORK : Air diving service. Assistance Pipe Laying and hidrostatic test
WORK DURATION : 3 MONTHS

1991
CLIENT : SAIPEM / ELF
VESSEL : DLB CASTORO 2
LOCATION/PROJECT : PESCARA, ITALY - ROSPO MARE Field Project
TYPE OF WORK : Air diving services. Assistance Jacket installation ROSPO C
WORK DURATION : 40 DAYS

1991
CLIENT : SAIPEM / ELF
VESSEL : DLB CASTORO 2/DSV RAGNO 2
LOCATION/PROJECT : ROSPO MARE C Field - PESCARA - (ITALY)
TYPE OF WORK : Independent Sub Contractor - Air / Saturation diving service. 16" Risers, Tie - in spools installation. Hydrostatic test
WORK DURATION : 2 MONTHS

1991
CLIENT : SAIPEM / AGIP
VESSEL : Barge VILLIENA
LOCATION/PROJECT : PESCARA, ITALY - VOMANO River - GIOVANNA Field Project
TYPE OF WORK : Independent Sub Contractor - LUMP SUM WORK. Air diving service. Installation of stabilisation SARMAC mattresses and pipe supports
WORK DURATION : 20 DAYS

1991
CLIENT : SAIPEM / AGIP
VESSEL : DSV RAGNO 2
LOCATION/PROJECT : Ionian Sea, CROTONE - ITALY / LUNA Field Project
TYPE OF WORK : Independent Sub Contractor - LUMP SUM WORK. Air/Saturation diving. Construction, Installation of 14"+3" tie-in spools pieces Flooding, Pigging, Hydrostatic test
WORK DURATION : 40 DAYS

1991
CLIENT : SAIPEM / AGIP RECHERCHE CONGO
VESSEL :DB PEARL MARINE
LOCATION/PROJECT : CONGO - ZAF Field Project
TYPE OF WORK : Independent Sub Contractor - Air/Saturation diving service. Installation of n. 4 / 10" Tie-in spools and risers
WORK DURATION : 30 DAYS