COMPANY PROFILE
Reference List

Print/Stampa

1992
CLIENT : SAIPEM / AGIP / CESI
VESSEL : DSV TRANQUILLIDAD
LOCATION/PROJECT : PESCARA, ITALY - VOMANO River - GIOVANNA Field Project
TYPE OF WORK
: Air diving service. Assistance post trenching operations
WORK DURATION
: 30 DAYS

1992
CLIENT : PORTO PETROLI GENOVA
VESSEL : DSV RAVELLO
LOCATION/PROJECT : Ligurian Sea . GENOVA, ITALY - S.B.M. Oil Terminal Maintenance Project
TYPE OF WORK : Contractor - LUMP SUM WORK - Air / Saturation diving service. Special Maintenance of single buoy mooring. Hoses replacement on bottom manifold. Disassembling - maintenance assembling of surface rotating joint. N.D.T. on buoy structures and sea - line. Hydrostatic final test
WORK DURATION
: 30 DAYS

1992
CLIENT : SAIPEM / AGIP
VESSEL : Barge AMEDEO / DSV BAO BAB / DSV KALIL
LOCATION/PROJECT : Adriatic Sea - RAVENNA, ITALY - AMELIA Field Project
TYPE OF WORK : Independent Sub Contractor - LUMP SUM WORK - Air diving. Construction, Installation of n. 12 Tie-in spools. Installation of risers clamps and risers. Pipeline Flooding, Pigging, Hydrostatic test
WORK DURATION : 2 MONTHS

1992
CLIENT : SAIPEM / AMOCO
VESSEL : DLB CASTORO 8
LOCATION/PROJECT : TRINIDAD TOBAGO
TYPE OF WORK : Independent Sub Contractor - Air /Saturation diving service. Installation of 24" risers and tie-in spools pieces
WORK DURATION : 2 MONTHS

1992
CLIENT : SAIPEM /AGIP
VESSEL : HLV PEARL MARINE
LOCATION/PROJECT : Adriatic Sea - Off-Shore Ravenna-Ancona at Barbara - Garibaldi Fields
TYPE OF WORK :Air diving service. Assistance of Jackets installation BARBARA H - GARIBALDI D
WORK DURATION : 3MONTHS

1992
CLIENT : SAIPEM / TMPC / SNAM
VESSEL : DLB CASTORO 2 / LBCASTORO 6 / DSV BAR PROTECTOR / DSV RAGNO DUE
LOCATION/PROJECT :SICILY CHANNEL - MESSINA STRAIT, ITALY - TRANS MED Project
TYPE OF WORK :Air / Saturation diving service. Assistance 24" pipe laying, post trenching operations with PTM"GIANO", Pipe stabilisation, Hydrostatic test
WORK DURATION : 3 MONTHs


1992 / 1993
CLIENT : SAIPEM AG / AGIP RECHERCHES CONGO
VESSEL : CASTORO DLB 8
LOCATION/PROJECT : Off-Shore POINTE NOIRE, CONGO - ZAP Project
TYPE OF WORK :Air/Saturation diving service. Pipe laying assistance, Tie-in spools and risers installation
WORK DURATION : 3MONTHS


1993
CLIENT :SNAM / BONATTI
VESSEL : TICINO
LOCATION/PROJECT : TICINO RIVER - ITALY
TYPE OF WORK :Air diving services. Pipe and Electric cables crossing on river. Post trenching operations
WORK DURATION : 30 DAYS

1993
CLIENT : SAIPEM / TMPC - SNAM
VESSEL : D.S.V. RAGNO 2
LOCATION/PROJECT : SICILY CHANNEL - ITALY
TYPE OF WORK :Air diving service. Assistance to post trenching with PTM"GIANO" from 20 to 35 mt water depth
WORK DURATION : 3 MONTHS


1993
CLIENT : SNAM / SOCIETà ITALIANA GRAGAGGI
VESSEL : DSV ECOLFIUMICINO
LOCATION/PROJECT : SICILY MORTELLE - ITALY
TYPE OF WORK :Independent Sub Contractor - LUMP SUM WORK - Air diving service. Pipe cutting and removal. Installation of Plidco flange and Williamson stopple
WORK DURATION : 40 DAYS


1993
CLIENT : PORTO PETROLI GENOVA
VESSEL : D.S.V. RAVELLO
LOCATION/PROJECT : Ligurian Sea - GENOVA, ITALY - S.B.M. Oil Termianl Project
TYPE OF WORK :Contractor - LUMP SUM WORK - Air /Saturation diving service - Removal / Recovery of damaged mooring structure of S.B.M. - N.D.T. on welds of riser bend and spool pieces at terminal platform. Application of epoxy compound on checked weld
WORK DURATION : 30 DAYS

1993
CLIENT : SAIPEM / AMOCO
VESSEL : DLB CASTORO 8
LOCATION/PROJECT : TOBAGO / TRINIDAD - IMMORTELLE FLAMBOUYANT Field Project
TYPE OF WORK : Indepemdent Sub Contractor - Air /Saturation diving service. Assistance Jacket positioning. Risers and Spool-pieces installation. Assistance Hydrostatic test
WORK DURATION : 2 MONTHS

1993
CLIENT : PORTO PETROLI GENOVA S.p.A.
VESSEL : D.S.V. RAVELLO
LOCATION/PROJECT : Ligurian Sea - S.B.M. GENOVA - ITALY
TYPE OF WORK : Contractor - LUMP SUM WORK. Air /Saturation diving service. Installation of new mooring structure on S.B.M.
WORK DURATION : 20 DAYS

1993
CLIENT : SAIPEM / TMPC / SNAM
VESSEL :D.S.V. RAGNO 2
LOCATION/PROJECT : SICILY CHANNEL - MESSINA STRAIT, ITALY
TYPE OF WORK :Air /Saturation diving service. Assistance Post trenching operations with PTM "GIANO" on existing 24" pipeline. Assistance pipeline hydrostatic test
WORK DURATION : 3 MONTHS

1993
CLIENT : SNAM / BONATTI
VESSEL :
LOCATION/PROJECT :RIVER PO - ASTI - ITALY
TYPE OF WORK : Contractor - Air diving service. Assistance Pipeline crossing on Po river
WORK DURATION : 3 DAYS

1993
CLIENT : SAIPEM / SNAM
VESSEL : D.S.V. KALIL
LOCATION/PROJECT : MESSINA STRAIT - ITALY
TYPE OF WORK : Independent Sub Contractor - Air Diving service. Repair of damaged Sealine
WORK DURATION : 25 DAYS

1993
CLIENT : EMC / TMPC
VESSEL :D.S.V. BAR PROTECTOR / LB CASTORO 6
LOCATION/PROJECT : SICILY CHANNEL - ITALY
TYPE OF WORK : Air/Saturation diving service. Assistance 24" pipe laying
WORK DURATION : 2 MONTHS

1994
CLIENT :SAIPEM / AGIP
VESSEL : D.S.V. RAVELLO
LOCATION/PROJECT :Adriatic Sea - ITALY
TYPE OF WORK : Independent Sub Contractor - LUMP SUM WORK - Saturation diving service. Risers-Spools installation at Ptf GARIBALDI, AGOSTINO, BARBARA Fields. Pipelines Flooding, Pigging, Hydrostatic test
WORK DURATION : 30 DAYS

1994
CLIENT : SAIPEM / TMPC
VESSEL : D.S.V. RAGNO 2
LOCATION/PROJECT : SICILY CHANNEL - ITALY
TYPE OF WORK : Air /Saturation diving service. Assistance to Post Trenching operations on 24" existing pipeline with PTM "GIANO"
WORK DURATION : 2 MONTHS

1994
CLIENT : SAIPEM / ABB-LUMNS CORP
VESSEL : DLB CASTORO 8
LOCATION/PROJECT : CABINDA - ANGOLA
TYPE OF WORK :Independent Sub Contractor- Air/Saturation diving service. Assistance Jackets installation, West, East Kokongo
WORK DURATION : 3 MONTHS

1994
CLIENT : SAIPEM / AGIP
VESSEL : DLB CASTORO 2 / D.S.V. KALIL / D.S.V. RAVELLO
LOCATION/PROJECT : Adriatic Sea - ANCONA - RAVENNA
TYPE OF WORK : Independent Sub Contractor - LUMP SUM WORK - Air/Saturation diving service. Clamps, riser, J-tubes and tie-in spools installation. As-laid survey. Assistance installation of Daria Jacket
WORK DURATION : 40 DAYS

1994
CLIENT : AGIP PETROLI
VESSEL :
LOCATION/PROJECT : ZHUHAI GUISHAN ISLAND - CHINA
TYPE OF WORK : LUMP SUM WORK - Inspection of wharf Oil terminal
WORK DURATION : 7 DAYS

1994
CLIENT : SAIPEM / AGIP
VESSEL : D.S.V RAGNO 2
LOCATION/PROJECT : Mediterranean Sea - Ptf PREZIOSO - SICILY
TYPE OF WORK : Independent Sub Contractor - LUMP SUM WORK - Air / Saturation diving service. Multiphase research program. Installation of U.W. pump unit MP.10 / Flow lines, control umbilical
WORK DURATION : 1 MONTH

1994
CLIENT : SAIPEM / BRITISH GAS - TUNISIA
VESSEL :D.S.V. RAGNO 2 - DLB CRAWLER
LOCATION/PROJECT : TUNISIA - MISKAR PROJECT
TYPE OF WORK : Air/Saturation diving service. Assistance pipe laying, spool pieces installation, Post trenching operation with PTM "GIANO". R.O.V. Service
WORK DURATION : 2 MONTHS

1994
CLIENT : SAIPEM
VESSEL :DLB CASTORO DUE
LOCATION/PROJECT : ST. EUSTATIUS - ANTILLES
TYPE OF WORK : Air/Saturation diving services. PLEM positioning, 48" Spool pieces and Single buoy mooring installation. R.O.V. Service
WORK DURATION : 2 months

1994
CLIENT : SAIPEM / MOBIL PRODUCING - NIGERIA
VESSEL :DLB CASTORO 8 / DSV RAGNO 2
LOCATION/PROJECT : NIGERIA - UBIT EXPANSION Project
TYPE OF WORK : Independent Sub Contractor - Air/Saturation diving service. Manifold and bridge installation, n. 8 of 24" spool pieces installation. Crossing preparation with Sarmac Mattresses. As Built survey
WORK DURATION : 3 MONTHS

1994
CLIENT : SAIPEM / EMPL
VESSEL :DLB CASTORO 2 / D.S.V. BAR PROTECTOR
LOCATION/PROJECT :GIBRALTAR STRAIT - MAROCCO
TYPE OF WORK : Independent Sub Contractor - Air diving service - Assistance pipe laying operation, Shore approach pulling - R.O.V. Service
WORK DURATION : 2 MONTHS

1994
CLIENT : SOCIETA' ITALIANA DRAGAGGI / EMPL
VESSEL :D.S.V. KALIL
LOCATION/PROJECT :GIBRALTAR STRAIT - MAROCCO
TYPE OF WORK : Air Diving Service. Tie.ins installation
WORK DURATION : 1 MONTH

1994
CLIENT : SAIPEM / AGIP
VESSEL :D.S.V. RAVELLO / DLB CASTORO 2
LOCATION/PROJECT : Adriatic Sea
TYPE OF WORK : Independent Sub Contractor - LUMP SUM WORK. Air/Saturation Diving Services. Assistance pipe laying BARBARA T - BARBARA H - Spool pieces installation. Crossing preparation, installation of stabilisation mattresses. R.O.V. Service. Hydrostatic test
WORK DURATION : 2 MONTHS